Particulars(In Crores/MWp) | 2013-14 | 2014-15 | 2015-16 | 2016-17 | |
---|---|---|---|---|---|
1 | PV Modules | 3.2592 | 3.658 | 3.3235 | 3.2839 |
2 | Land Cost | 0.168 | 0.25 | 0.25 | 0.25 |
3 | Civil and General Works | 0.945 | 0.6 | 0.5 | 0.35 |
4 | Mounting Structures | 1.05 | 0.5 | 0.5 | 0.35 |
5 | Power Conditioning Units/Inverters | 0.6 | 0.5 | 0.45 | 0.35 |
6 | Evacuation Cost upto inter-connection point (cables and transformers) | 1.05 | 0.6 | 0.55 | 0.44 |
7 | Preliminary and pre-operative expenses including IDC and contigency | 0.8 | 0.69 | 0.485 | 0.2763 |
8 | Others | 0.098 | 0.110 | ||
Total(In Crores/MWp) | 7.97 | 6.91 | 6.0585 | 5.3002 |