CERC Benchmark Costs

Particulars(In Crores/MWp)2013-142014-152015-162016-17
1PV Modules3.25923.6583.32353.2839
2Land Cost0.1680.250.250.25
3Civil and General Works0.9450.60.50.35
4Mounting Structures1.050.50.50.35
5Power Conditioning Units/Inverters0.60.50.450.35
6Evacuation Cost upto inter-connection point (cables and transformers)1.050.60.550.44
7Preliminary and pre-operative expenses including IDC and contigency0.80.690.4850.2763
8Others0.0980.110
Total(In Crores/MWp)7.976.916.05855.3002
Source : CERC