SECI announces results of Financial Bid opening – Solairedirect, Azure, Sun Edison among winners

SECI had earlier released the list of qualified bidders with an announcement that the financial bids would be opened on 21st February 2014. The opening of the financial bids has now concluded and the preliminary results are available. A cursory glance at the results bring out some interesting facts. Some notable companies to bag allocations […]

SECI announces results of Financial Bid opening – Solairedirect, Azure, Sun Edison among winners Read More »

JNNSM Phase 1 plant performance data for January 2014 released by MNRE

MNRE released the performance data for plants under JNNSM for the month of January 2014. As usual, the projects are under 4 different sections. The details of each one is given below. (Note: Please click on the image to enlarge it) JNNSM Phase 1 Batch 2 JNNSM Phase 1 Batch 1 JNNSM Phase 1 Migration

JNNSM Phase 1 plant performance data for January 2014 released by MNRE Read More »

JNNSM – Solar Plant Performance for December 2013 released ; CSP plant performance data released for the first time

In the latest data on solar plant performance released by MNRE, a majority of the plants have shown a marginal dip in generation in December 2013 compared to the previous month. The dip can be attributed to reduced irradiation levels.  (As per meteonorm data for Phalodi in Rajasthan, the irradiation level is the lowest during

JNNSM – Solar Plant Performance for December 2013 released ; CSP plant performance data released for the first time Read More »

India adds 1004 MW solar capacity in 2013 and Wind capacity crosses the 20 GW mark – MNRE

According to the data released by the MNRE today, India’s cumulative grid-connected solar installed capacity(PV+CSP) stood at 2,180 MW as of 31 December 2013. This translates to an addition of 1,004 MW in the calender year 2013. Wind installations crossed the 20 GW mark in November 2013, and stood at 20,150 MW at the end of 2013. The total

India adds 1004 MW solar capacity in 2013 and Wind capacity crosses the 20 GW mark – MNRE Read More »

SECI announces clarifications to queries from stakeholders (JNNSM Batch 2)

The Solar Energy Corporation of Indian (SECI) had earlier released the standard PPA and VGF securitization agreement following which a pre-bid meeting was scheduled to clarify the details under the RfS as well as the PPA and VGF agreements. SECI has now released the clarifications to the queries raised in the pre-bid meeting. A highlight

SECI announces clarifications to queries from stakeholders (JNNSM Batch 2) Read More »

India Solar – Solar PV plant performance data for October 2013 released by MNRE

Within less than 2 weeks of releasing the data for September 2013, MNRE today released the plant performance data for October 2013. The data for some of the plants is missing, while for the majority of the plants, it is available. The data under different schemes are given below. Click on the images to enlarge

India Solar – Solar PV plant performance data for October 2013 released by MNRE Read More »